Our first wee house in a backyard is done! #14 under Boulder’s revised ADU regulations. Its total cost, excluding land, in 2019-2020 was $190,600, at 540sf that translates to $353/sf.
Our second wee house in a backyard is under design. This one is substantially different. For one, lumber costs have more than doubled in cost and preliminary cost came in at almost $500/sf. A 41% overall increase! Plus – Boulder adopted the IECC’s 2018 energy conservation standards. But wait, there is more – COVID-19 happened and the city approval process is spiraling in excess and redundancy. Yikes. I, however, remain undeterred in building ADUs to change the way we make small houses and use our urban land. ADUforMe and Studio Points are making their way through all of this. We bring a solution to the table. Coming soon…the Poche_Truss!